Saint Louis, MO asked in Construction Law and Contracts for Missouri

Q: Roofer took 9,000 down payment in Nov’21 signed a contract & roof wasn’t done until Nov 2022 Is the contract still valid

He used our money for his own purposes & then couldn’t afford to replace it, fed me lie after lie, I chased him down for a year. His dad finally loaned him the money so I wouldn’t press charges. I paid for all materials/labor. Finished the roof a year later Nov 2022. Now he wants to be paid $4000. Do I have to give him money after he stole mine & never put a dime of his own into the job? He, all subcontractors and supply companies signed unconditional lien wavers.

Related Topics:
2 Lawyer Answers
Ronald J. Eisenberg
Ronald J. Eisenberg
Answered
  • Chesterfield, MO
  • Licensed in Missouri

A: Your contract governs. I think you misstated something. You claim that you entered into the contract in November 2021 and he finished the work in November 2022. We are only in early April 2022. Although it took longer than expected for him to finish the roof, unless you’ve suffered financial damages from the delay, I’m not sure of your basis for believing you needn’t pay for the work done. Also, even if you received a lien waiver, that doesn’t prevent a suit for breach of contract.

Robert Grant Pennell agrees with this answer

Robert Grant Pennell
Robert Grant Pennell
Answered
  • Manchester, MO
  • Licensed in Missouri

A: As usual, Mr. Eisenberg is correct - the contract governs. You state the initial $9k paid was a down payment, but what was the originally agreed-upon price? You also state that you paid for all of the materials. Was that the original understanding or something that you arrived at to get the work completed. The reason I ask these questions is to clarify what you actually owe for the remaining work since the $9k was a down payment.

I can certainly appreciate your frustration with having to chase this guy down as well as the delay in getting the work finished. However, the delay in doing the work does not alter your obligation to pay for the work in full. If the delay caused damage to the roof or other property, then you may have a claim for those damages, but you still must pay for the agreed-upon work. Similarly, if the delay caused there to be additional work that had to be done, you should not have to pay for that additional work.

If the original agreement was for you to supply the materials with an agreed-upon price of $13k, of which you have only paid $9k, then you are obligated to pay the remaining $4k. At best, you may be able to argue that the delay caused the price of materials (for which you paid) to increase.

Justia Ask a Lawyer is a forum for consumers to get answers to basic legal questions. Any information sent through Justia Ask a Lawyer is not secure and is done so on a non-confidential basis only.

The use of this website to ask questions or receive answers does not create an attorney–client relationship between you and Justia, or between you and any attorney who receives your information or responds to your questions, nor is it intended to create such a relationship. Additionally, no responses on this forum constitute legal advice, which must be tailored to the specific circumstances of each case. You should not act upon information provided in Justia Ask a Lawyer without seeking professional counsel from an attorney admitted or authorized to practice in your jurisdiction. Justia assumes no responsibility to any person who relies on information contained on or received through this site and disclaims all liability in respect to such information.

Justia cannot guarantee that the information on this website (including any legal information provided by an attorney through this service) is accurate, complete, or up-to-date. While we intend to make every attempt to keep the information on this site current, the owners of and contributors to this site make no claims, promises or guarantees about the accuracy, completeness or adequacy of the information contained in or linked to from this site.