Q: How do I recover a down payment to a general contracting company that is making no effort to communicate or do the work?
Contract signed for project and down payment paid in March. Contractor never contacted me again. I complained to the contractor company then was given a new contractor who is doing the same as the prior contractor. Verbally, the agreement with the first contractor and second contractor was to have work completed no later than end of May. Both said that wouldn't be a problem. Now they won't return calls and company won't return calls (it's been weeks). I'd like to "fire" them and receive my deposit back. Is that an option given there is a signed contract with no date of work noted?
A:
It depends on the nature of the job and what a reasonable time for completion of that particular job is.
In a contract, the parties usually must explicitly agree on a firm completion date if it is important to the parties when the work must be performed. The phrase used to describe this is: "Time is of the essence." Otherwise, the law presumes that the work must be performed in a reasonable time depending on the nature of the work and the surrounding circumstances. In construction contracts, some circumstances that may be important are the weather and the availability of the materials to be used in the work.
Before terminating a construction contract, it is usually better to give the contractor written notice and an opportunity to cure. For example, you might say "a reasonable period of time to complete the work has passed" and that the contractor should cure its failure to perform by "commencing work within 10 days and completing the project in its entirety within 30 days" if those times are reasonable given the nature of the work. You might also ask the contractor to give you notice "if there are exigent circumstances justifying a further delay in commencing the work."
A:
Recently had a decision from the Fifth District that held that the contract did not have a completion date, and the contract did not state that "time was of the essence", therefore the absence from the project for even a long period of time was not a material breach. Attempting to "fire" the contractor could be a breach on your part.
I would suggest that you provide a notice of default, stating the last time that you had contact and that unless the contractor made contact with you, you would consider that he abandoned the contract and that you would consider him to be in default. A notice of default should then be issued giving the contractor 60 days to cure the default.
Justia Ask a Lawyer is a forum for consumers to get answers to basic legal questions. Any information sent through Justia Ask a Lawyer is not secure and is done so on a non-confidential basis only.
The use of this website to ask questions or receive answers does not create an attorney–client relationship between you and Justia, or between you and any attorney who receives your information or responds to your questions, nor is it intended to create such a relationship. Additionally, no responses on this forum constitute legal advice, which must be tailored to the specific circumstances of each case. You should not act upon information provided in Justia Ask a Lawyer without seeking professional counsel from an attorney admitted or authorized to practice in your jurisdiction. Justia assumes no responsibility to any person who relies on information contained on or received through this site and disclaims all liability in respect to such information.
Justia cannot guarantee that the information on this website (including any legal information provided by an attorney through this service) is accurate, complete, or up-to-date. While we intend to make every attempt to keep the information on this site current, the owners of and contributors to this site make no claims, promises or guarantees about the accuracy, completeness or adequacy of the information contained in or linked to from this site.